Schedule Harvesting

Use the Status column in the Harvest Dataverse list to enable or disable scheduled harvesting as follows:

  1. Navigate to the Network homepage, and click Network Options.
    You see the [Your] Dataverse Network Admin Options page.
  2. Scroll to the Dataverses, Harvesting, Exporting, and OAI Sets options, and then click Manage Dataverses.
    You see the Manage Dataverses page.
  3. If a schedule is set up but is not active, the message Not Scheduled is displayed in the row for that dataverse. A Schedule Haravesting button appears beside the message.
    If a schedule is set up and is active, the message Scheduled is displayed, and an Unschedule Haravesting button appears.
    To enable harvesting on the configured schedule, click the Schedule Harvesting button.
    To disable harvesting on the configured scheduled, click the Unshcedule Harvesting button.